A look ahead
Traffic impacts, work plans
The new interchange project will take three work seasons to complete and it's looking like 2029 will be the most impactful with a full closure at the intersection.
Overall, motorists will encounter changes as they navigate through this area of Baxter. Detours will be necessary to work beneath the road, elevate the road and construct bridges.
Hwy 371 and 210 will have reduced speeds, shoulder or single-lane closures at off-peak times during the full duration of this project. Off-road work to occur year round.
Expect to see crews and equipment prior to this project as they relocate utilities, survey locations, aquire right of way, test materials and more. The city of Baxter will work on area improvements in 2027 in preparation of this project.
Access to businesses will be maintained.
Schedule at a glance
Timeframe |
Map color |
Key work |
Impacts |
2028 spring-fall Prepare |
Purple |
Prepare work areas for 2029 construction (PNG map);includes frontage roads, temporary lane widening and the Excelsior Rd./Dellwood Dr. roundabout
|
|
2029 spring-fall Construct |
Orange |
Construct interchange and connections (PNG map); includes roads, bridges, roundabouts, pedestrian facilities |
Full intersection closure. Hwy 210 and Hwy 371 reduced to one-lane of traffic and detoured around the closure:
|
2030 spring-early summer Wrap up |
Blue |
Wrap up and remaining work (PNG map); reconnect Excelsior Rd. between the new Dellwood Dr. roundabout and the Edgewood Dr. roundabout under the Hwy 371 bridge; establish turf in all areas |
|
*All information is tentative and subject to change until contractor is on board. Materials, weather and unexpected items found beneath the road can also change schedules. Off-road work to occur year round on this project.