Hwy 19/College Drive Reconstruction

Marshall

About this project

Summary of MnDOT work

map of Hwy 19/College Dr. project showing work zone areas
  • MnDOT is reconstructing Highway 19/College Drive from 700 ft west of Marlene St through the intersection of Bruce Street in the City of Marshall.
  • The City of Marshall is replacing sanitary sewer and water main utilities.
  • A single-lane roundabout will be constructed at the intersection of Highway 19/College Drive, Country Club Drive, and South 2nd Street.
  • An EV Charging Station will be installed in the Avera parking lot.
  • Sidewalk improvements will be made along the project area to improve accessibility.
  • Several traffic control changes throughout the route will be made to enhance safety.
  • A bike lane will be striped from Marlene St. to just west of Fairgrounds Rd.

Tree Planting Project

  • Begins August 10 and runs through November.
  • Tree planting is contracted through Hoffman and McNamara Co.
  • This project is run as a completely separate project from the road construction. If you see contractors working on your boulevard, they are preparing the areas for new trees.
  • Tree planting project map.
  • Tree selections can be viewed here(PDF), please note, these are subject to change.
  • For questions contact Project Manager Diana Heston, 320-979-3327, diana.heston@state.mn.us

Tree project update: September 17

Tree bed areas from Main Street West to Marlene Street (Year 1 College Drive Project) are complete. Crews will work on Year 2 areas as College Drive construction work progresses.


Road Construction Project Update: September 17, 2026

Marshall Street to Bruce Street 

  • Concrete paving was completed at the Marshall Street and Highway 19 intersection.
  • Curb and gutter was poured for the new concrete median at Marshall Street. Reminder: Marshall Street and Highway 19 intersection will now be a right-in/right-out only. There is a center median that is being built in this intersection. There will be signage on the median to direct traffic.
  • Concrete paving was completed on all the side streets - North 3rd Street, Park Avenue, Whitney Street, Hill Street and Minnesota Street.
  • Concrete footings were dug, formed and poured for crossing equipment between Whitney Street and High Street.
  • Work continues on ADA components.
  • Permanent signs were installed from Main Street to Marshall Street as well as Bruce Street.
  • EV charging station work resumed in the Avera parking lot/Bruce Street boulevard.
  • Paving preparation work has been completed on all the side street connections and driveways.
  • Topsoil placement has begun on the boulevards.
  • Utility work continues.

Next week Marshall Street to Bruce Street. All work is weather permitting.

  • Concrete work will continue with pouring the sidewalk, driveways and ADA components.
  • Concrete work is scheduled to be completed on the center median at Marshall Street and Highway 19.
  • Paving is scheduled to be completed on all side street driveways.
  • Concrete will be curing, hardening and gaining strength before traffic use.
    • 2025: Stages 1-4

      Mapping and Detour for the 2025 construction season - stages 1 through 4

      2026: Stages 5-7

      Year 2 map and detour with stages 5 through 7