85th St. bridge over Hwy 52

North of Rochester

About this project

Traffic impacts

Project detour map
View full-size detour map (JPG).

Check 511mn.org or the free app to see traffic impacts.

  • A single lane closure on Highway 52 southbound at the 85th Street bridge will continue into October.
  • One lane will remain open on 85th Street bridge the majority of the time. Traffic signals will be used to direct motorists through the project in a single lane.
  • Short-term lane closures and detours of Highway 52 will occur during some of the work. The detours will be announced ahead of time.
      • The Highway 52 southbound closure will occur while crews pour concrete on the 85th Street bridge deck. The current schedule has the detour starting at at 7 p.m. on Monday, Sept. 21. It is expected that the road will reopen to traffic by 5 a.m. or earlier on Tuesday, Sept. 22.
      • Detour: From Highway 52 southbound, take Exit 64, turn left on Olmsted County Road 112/ 100th Street NW, turn right on Olmsted County Road 112/ 18th Avenue NW, turn right on Highway 63 (75th Street NW), then take the ramp to Highway 52.

Summary of work

Project area map
View full-size project area map (JPG).

Crews started repairing the 85th Street NW bridge over Highway 52 north of Rochester Aug. 20, 2026. Repairs are being made due to a crash at Highway 52 southbound lane under the bridge. Work is expected to be completed in fall 2026.