Construction begins June 2025
Current impacts
Off-road work to occur year-round. All traffic impacts are tentative and weather dependent.
Prep work in progress
Periodic lane, shoulder closures or flaggers controlling traffic as crews prepare work areas along Hwy 10, Hwy 29, Hwy 71:
- April-June: Relocate utilities
- May-June: Install temp crossovers on Hwy 10, set-up traffic control devices and demo buildings