Hwy 65—Cambridge to north of Braham

Includes Grandy, Isanti and Kanabec counties

Work, detour begins Tue, July 7

Shoulder closures and off-road work to occur anytime from Cambridge to north of Braham

Hwy 65 - Stanchfield to Cambridge

July 7 to late summer

Through traffic
Local traffic

Work zone open to businesses, visitors and residents

  • Expect delays, reduced speeds, narrow lanes, flaggers, hard closures between side roads to work beneath the road, changes to access, reduced speeds, gravel or grooved surfaces
Truck traffic

About this project

MnDOT will resurface and update over 10 miles of Hwy 65 from south of 357th Ave. NE at the end of four-lane in Cambridge to south of Kanabec Co. Rd. 45/120th Ave. north of Braham, includes drainage and sidewalks in Grandy.

Hwy 65 work location map between Braham and Cambridge
Hwy 65 work Cambridge to north of Braham. Select PNG image to enlarge

Work highlights

  • Resurface 10 miles of road surface (cold-in-place recycle*)
  • Add northbound left turn lane on Hwy 65 at 357th Ave. NE north of Cambridge
  • Replace pipes and box culverts at multiple locations under Hwy 65
  • Update or repair guardrail
  • Add Hwy 65 intersection lighting at:
    • Isanti Co. Rd. 6 and Co. Rd. 4
    • Kanabec Co. Rd. 4 and Co. Rd. 16 (King Rd.) 
  • Install centerline/shoulder mumble strips and paint new pavement marking
  • Make any other necessary repairs

Grandy

  • Resurface road
  • Replace underground storm sewer
  • Upgrade pedestrian sidewalks
  • Extend center left-turn lane

About cold-in-place recycle*

This road surface treatment and equipment is being used on this project. The process involves a convoy of equipment to finish a road surface, including tankers that hold emulsion material and water, milling or crushing and recycling machines, pavers and rollers.

Traffic plans: July-fall 2026

Crews will work on two segments of Hwy 65—Stanchfield to Cambridge and Stanchfield to north of Braham. Motorists can expect lane or road closures with detours, no shoulders and one-way traffic, at times.

The project focuses on two work tasks:

  1. Replace or repair underground pipes, update the road or accesses and sidewalks.
  2. Revive the road surface (cold-in-place recycle*).
Hwy 65 work location map between Braham and Cambridge
Hwy 65 traffic plan of detours, one-way traffic from Cambridge to north of Braham. Select PNG image to enlarge

Schedule at a glance

Tentative work, schedule and detour plans

2026 Hwy 65 Work Impacts
Begins July 7 - late summer Stanchfield to Cambridge Pipe work and make other repairs south of Co. Rd. 3, widen road to add turn lanes and update sidewalks in Grandy
  • Both directions closed and detoured (PNG) via Co. Rd. 3 Stanchfield, Co. Rd. 36, Co. Rd. 34 and Co. Rd. 30 Cambridge
  • Late summer Stanchfield to Cambridge Road surface
  • Northbound Hwy 65 closed and detoured (PNG) via Co. Rd. 30 Cambridge, Co. Rd. 34, Co. Rd. 36 and Co. Rd. 3 Stanchfield.
  • Southbound Hwy 65 one-way traffic between Co. Rd. 3 Stanchfield to Co. Rd. 30 Cambridge
  • Late summer-fall Stanchfield to Brunswick Pipe work and make other repairs north of Co. Rd. 3
  • Both directions closed and detoured (PNG) via Isanti Co. Rd. 3 Stanchfield, Co. Rd. 14/4 and Kanabec Co. Rd. 16
  • Late summer-fall Stanchfield to Brunswick Road surface
  • Northbound Hwy 65 one-way traffic (PNG) north of Co. Rd. 3
  • Southbound Hwy 65 closed and detoured via Kanabec Co. Rd. 16, Co. Rd. 14/4 and Co. Rd. 3
  • Truck route (PNG): Hwy 23 south of Mora to Hwy 47 Ogilvie to Hwy 95 Pine Brook to Cambridge or seek other route to avoid delays.

    Local access

    Hwy 65 will be maintained to those who live, work or visit those within the closed work zone; however, hard closures will be necessary at times to work under the road. Enter/exit nearest your destination, use alternate entrances or back streets.

    For east (Braham) or west (Grady) access follow road signs to/from Co. Rd. 3 and Hwy 65.

    Construction plans are tentative and subject to change by weather, supplies or contractor.