MnDOT appreciates the community’s patience throughout this six-month project, including area detours. Crews will remove detour signs and finish final turf and guardrail updates through Fri, Oct. 30.
Detour lifted Fri, Oct. 23, included the alliway stop at Co. Rd. 26.
MnDOT improved five miles of Hwy 169 from south of Garrison at Crow Wing Co. Rd. 26 to north of Garrison at Pike Ave. Work included city storm sewer, sidewalk and a new roundabout at the busy Hwy 18 intersection.
Highlights
Select map to enlarge (PNG)
In Garrison
Reconstruct Hwy 169 from the north and south city limits, includes adjacent entrances and road approaches - complete
Construct a four-legged single lane roundabout at the intersection of Hwy 169, Hwy 18 and Monroe St. - complete
Install new city storm sewer - complete
Update or add pedestrian sidewalk and approaches
Upgrade lighting
North and south of Garrison
Resurface (mill and overlay) from south of Co. Rd. 26 to south of Hwy 18 in Garrison
Resurface north of Hwy 18 to Pike Ave., one mile north of Hwy 18 - Complete