Traffic impacts
Motorists can expect lane and shoulder closures during daytime hours through August 1. Cross streets and business accesses will experience intermittent closures during active work. Closures to driveways will be coordinated with businesses and residents.
Night work will start Sunday, Aug. 2. Paving work will require lane closures between the hours of 8 p.m. and 6 a.m. and all signalized intersections will be put in a four-way flashing stop condition. Connecting streets will be closed for up to two hours while the pavement seal coat cures. This work is expected to occur for six consecutive nights, weather permitting.
Following this work, the project will be suspended for 14 days to allow for cure time. Permanent striping will also be installed during night work.