Hwy 13 at Nicollet Avenue Interchange

SP 1901-207 Letting Aug. 19, 2026

Purpose

To replace the traffic signal at Hwy 13 and Nicollet Ave in the City of Burnsville with a grade-separated interchange.

Procurement schedule

  • Request for Letters of Interest - Aug. 20, 2025
  • RFQ: Jan. 6, 2026
  • Draft RFP: Late March 2026
  • RFP: Late May 2026
  • Letting: Aug. 19, 2026
  • Construction start: 2027

Information

Oversight

  • Design and construction post-letting oversight will utilize consultant contracts